Lou Ogden (Myslony) Bridge & Waterline

Project Staff Contact: 
Casey Fergeson, Project Engineer
Project Type:
Capital Project
Transportation
Project Status: 
Completed
Location: 
Myslony Street
Tualatin

This capital project involves designing and constructing a bridge to extend Myslony Street over Hedges Creek to 112th Avenue in the industrial area between SW Herman Road and SW Tualatin-Sherwood Road. This includes extending a waterline along the bridge corridor. Design was completed in 2017 and construction began February 2018. Wildish Construction is the contractor on this project. Construction was completed in the winter of 2018.

If you have questions about this project please contact Project Engineer Casey Fergeson  at 503-691-3034 or cfergeson@tualatin.gov.

 

Myslony Bridge and Waterline Project Location Map
Bridge rebar construction
Setting bridge slabs