63rd Avenue Waterline Replacement

Project Staff Contact: 
Matt Palmer
Project Type:
Capital Project
Water
Project Status: 
Completed
Location: 
Location

The City is replacing the 8 inch waterline located in 63rd Avenue.  The project began at the intersection of 63rd Avenue and Lower Boones Ferry Road, and extends approximately 350 feet north in 63rd Avenue.

Design work was completed in 2017. Construction was awarded to Trenchline Excavation, Inc. in November 2017.

Construction began in March 2018 and was completed in April 2018.

All work was performed at night (from 9 pm to 5 am) in order to avoid disrupting businesses in the area. Potential traffic impacts include half street closure (not a full closure) and flaggers directing traffic. Access to businesses remained open during construction. 

For questions or concerns please contact Engineering Associate Matt Palmer at 503-691-3059 or mpalmer@tualatin.gov.