This project includes the replacement of the existing reservoir roof, replacement of the upper shell courses, and interior/exterior recoating of the C-1 Water Reservoir. Design was completed in January 2018 and the construction contract was completed in November 2018.

Construction Schedule:
  • June 2018 – Paint and coatings removal on lower shell courses. Prime lower shell courses.
  • July to September 2018 – Demolition of existing roof structure, upper shell courses, and miscellaneous appurtenances (e.g. interior and exterior ladders). Installation of new upper shell courses, roof structure, and appurtenances.
  • September to November 2018 – Application of new interior and exterior coatings.

For questions or concerns please contact Project Engineer Casey Fergeson at 503-691-3034 or by email at cfergeson@tualatin.gov.