Right of Way Permit (ROW)

A Right of Way Permit is required to complete any work fronting residential or commercial properties within the right-of-way

 

In order to fulfill the requirements of the permit application process, the following tasks will need to be completed:

1.   Confirm your Contractor is licensed by the Oregon Construction Contractors Board using the State’s online CCB search tool: Contractor License Search

2.   Complete a Right of Way Permit Application using the City's online Web Portal, eTrakit.

3.   Upon online application, pay a deposit fee as set forth in the City of Tualatin Fee Schedule

4.   You are required to provide financial assurance for performance of the work, in an amount equal to twice the cost of construction as approved by the City Engineer.

  • For example, if the job amount is $4,000 the financial assurance would be $8,000.  This assurance is to ensure that the applicant constructs and completes all required improvements within the public right of way, as described in Tualatin's Public Works Construction Code, Section 102.14.00
  • Financial assurance payment can be made by: 
    • Bond by a licensed bonding agency using the City's Bond Template;
    • Cash;
    • Check made payable to The City of Tualatin.

5.   Provide proof of Contractor's Insurance and Indemnification as set forth in Section 102.6.1 of the Public Works Construction Code.

 

--- For Right of Way Permit inquiries or Inspection Requests, please call 503-692-2010, or email here ---